Are Liquidated Damages Clauses Enforceable in New York? What Business Owners Need to Know

Updated: Nov 6
Updated October 21, 2026
You signed a two-year exclusive distribution agreement for your Queens-based food import business. Buried in the contract was a clause saying that if either party breached, they'd owe the other $500,000 in liquidated damages, no questions asked. Six months later, your distributor walked away and signed with a competitor. You're thinking that clause just handed you half a million dollars. But here's the problem: New York courts don't automatically enforce liquidated damages clauses, and the one in your contract might not survive judicial scrutiny.
Liquidated damages clauses appear in virtually every serious commercial contract in New York: construction agreements, supply deals, franchise contracts, commercial leases, and software licensing arrangements. When they work, they save you the brutal expense of proving actual damages at trial. When they don't, you're left scrambling to prove what you lost the hard way.
Key takeaways
New York courts enforce a liquidated damages clause only if the amount reasonably estimates probable loss and actual damages were hard to measure.
Courts judge the clause as of the day the contract was signed, not by how the losses later turned out.
The party attacking the clause must prove it is a penalty, and a bare claim that the amount is too high is not enough.
A flat sum chosen to discourage breach, rather than calculated from likely losses, can be struck down as a penalty.
If a court strikes the clause, your breach claim survives, but you must prove your actual damages the harder way.
What Is a Liquidated Damages Clause and Why Do Contracts Include Them?
A liquidated damages clause is a contract provision that sets a predetermined amount of damages payable if one party breaches. Instead of going to court and proving exactly how much the breach cost you, both sides agree upfront on a number. The clause essentially says: "If you break this deal, you owe $X."
Businesses use these clauses for practical reasons:
Certainty: both parties know the financial stakes from day one
Reduced litigation costs: proving actual damages in complex commercial cases is expensive and time-consuming
Difficult-to-measure harm: some breaches cause real damage that's nearly impossible to quantify precisely
Deterrence: a fixed penalty discourages casual breach
Speed: enforcement is faster when you don't need forensic accountants and expert testimony
But there's a catch. New York law draws a sharp line between a legitimate pre-estimate of damages and a penalty designed to punish breach. Courts will enforce the first and strike down the second.
When Will New York Courts Enforce a Liquidated Damages Clause?
New York courts apply a two-part test to determine enforceability. The clause must satisfy both prongs or it gets thrown out.
First, the liquidated amount must be a reasonable forecast of the probable damages that would result from a breach. This doesn't mean the number has to be exact, but it can't be wildly disproportionate to any plausible measure of harm. A $5 million liquidated damages provision in a $50,000 supply contract is almost certainly unenforceable.
Second, the actual damages must be difficult to ascertain at the time the contract is formed. If your losses from a breach would be straightforward to calculate (say, the difference between the contract price and the market price for a commodity), courts are more likely to view a liquidated damages clause as an unnecessary penalty rather than a practical solution to a measurement problem.
The Court of Appeals established this framework in Truck Rent-A-Center, Inc. v. Puritan Farms 2nd, Inc., 41 N.Y.2d 420 (1977), and it remains the controlling standard. The court emphasized that the analysis looks at conditions as of the time the contract was made, not in hindsight after the breach. A clause that seemed reasonable when the deal was signed doesn't become unenforceable just because actual damages turned out to be lower.
More recently, in JMD Holding Corp. v. Congress Financial Corp., 4 N.Y.3d 373 (2005), the Court of Appeals placed the burden on the party trying to avoid the clause. That party must show either that the damages were readily ascertainable when the contract was signed or that the amount is conspicuously disproportionate to the losses foreseeable at that time. The court upheld a lender's early termination fee because the borrower offered no factual proof that it was a penalty. The key question is whether the clause bore a reasonable relationship to foreseeable harm at the time of contracting, not whether it perfectly predicted the future.
When Do Courts Strike Down Liquidated Damages as an Unenforceable Penalty?
Courts refuse to enforce liquidated damages clauses when they function as punishment rather than compensation. Here are the red flags that get clauses invalidated:
Grossly Disproportionate Amounts
If the liquidated sum dwarfs any conceivable measure of actual harm, courts treat it as a penalty. A Manhattan landlord who includes a $1 million liquidated damages clause in a five-year lease worth $300,000 total is asking for trouble. The number needs to bear some rational relationship to the probable harm from breach.
A recent example: in Levin v. Salvini, 2026 NY Slip Op 01918 (1st Dep't 2026), the First Department held that a $1,000,000 flat fine for breaking a noncompete was an unenforceable penalty. The evidence showed the amount "was not calculated with any precision and was intended to sufficiently disincentivize disloyalty." The sum was also out of proportion to the fund's revenue, and the contract separately allowed recovery of actual damages.
Easily Calculable Damages
When actual damages can be determined through straightforward arithmetic (like the difference between a contract price and a readily available market price), courts question why a liquidated damages clause is necessary at all. The harder your damages are to measure, the more likely your clause survives.
One-Sided Clauses
Clauses that impose liquidated damages only on one party while leaving the other free to breach without penalty attract extra scrutiny. Courts don't automatically invalidate one-sided clauses, but the asymmetry can signal that the provision was imposed through unequal bargaining power rather than mutual agreement.
Forfeiture Provisions Disguised as Liquidated Damages
Some contracts require the breaching party to forfeit deposits, prepayments, or equity interests and label this a "liquidated damages" provision. New York courts look past the label to the substance. If the forfeiture is disproportionate to any reasonable estimate of harm, it's a penalty regardless of what the contract calls it.
Facing a Dispute Like This?
When real money is on the line, timing matters. Yassi Law represents New York business owners in partnership disputes, contract breaches, fraud claims, and commercial litigation. Call (646) 992-2138 or schedule a confidential consultation.
Understanding when courts will dismiss claims at the pleading stage is critical when structuring these provisions.
How Do Liquidated Damages Work in Specific Types of New York Commercial Contracts?
The enforceability analysis plays out differently depending on the type of deal.
Construction Contracts
Liquidated damages are extremely common in construction agreements, typically tied to delays. A clause imposing $1,000 per day for late completion is standard and generally enforceable because delay damages (lost revenue, extended financing costs, disrupted business operations) are genuinely difficult to calculate in advance. New York courts regularly enforce per-diem construction delay clauses when the daily rate reflects a good-faith estimate of the owner's daily losses. In Seymour v. Hovnanian, 211 A.D.3d 549 (1st Dep't 2022), the First Department enforced a $1,000-per-day delay clause between parties represented by counsel. The rate was about 2.3 times the actual daily loss, which the court found was not "grossly disproportionate" to the actual damages. The court also rejected the argument that smaller actual losses, seen in hindsight, defeat the clause.
Commercial Leases
Lease liquidated damages clauses get heavy scrutiny. New York's Real Property Law and strong tenant protections mean courts won't rubber-stamp punitive forfeitures. Clauses requiring the tenant to pay the entire remaining rent upon early termination, without any duty to mitigate, are frequently struck down as penalties. A more defensible approach calculates liquidated damages as the difference between the contract rent and the fair market rental value for the remainder of the term.
Franchise and Distribution Agreements
These agreements often include liquidated damages for early termination, non-compete violations, or failure to meet performance benchmarks. Because franchise relationships involve complex, hard-to-quantify damages (brand harm, market share erosion, recruitment costs for replacement franchisees), courts are often more willing to enforce reasonable liquidated damages provisions in this context. In NGM Mgt. Group, LLC v. Bareburger Group, LLC, 2024 NY Slip Op 00979 (1st Dep't 2024), the First Department upheld a franchise clause measured by average monthly royalty fees over two years or the remaining term, whichever was higher. Because the amount was based on royalty fees actually paid, the court found it bore a reasonable proportion to the probable loss. The franchisee's bare claim that the amount was disproportionate was not enough.
Software and Technology Contracts
Service-level agreements (SLAs) routinely include liquidated damages triggered by downtime, data breaches, or failure to meet performance metrics. Given the difficulty of proving the precise business impact of a four-hour system outage on a Brooklyn e-commerce company's revenue, these clauses typically survive challenge, as long as the amounts aren't wildly out of proportion to the service fees.
What Happens If the Clause Is Struck Down?
If a court finds your liquidated damages clause unenforceable, it doesn't kill your breach of contract claim. You still have the right to prove actual damages, but now you have to do it the hard way.
That means establishing your lost profits with reasonable certainty, hiring expert witnesses, gathering financial records, and convincing a judge or jury of the precise dollar amount you lost. The entire process that the liquidated damages clause was designed to avoid lands squarely in your lap.
This is why getting the clause right at the drafting stage matters so much. A poorly drafted liquidated damages provision doesn't just fail. It forces you into a more expensive, uncertain damages fight at trial.
Under New York's six-year statute of limitations for most breach of contract claims (CPLR 213), you have time to build that case, although contracts for the sale of goods are excluded and follow the separate deadline in article 2 of the Uniform Commercial Code. But proving actual damages months or years after the breach, without the benefit of contemporaneous damage calculations, is always harder than it sounds.
How Should You Draft a Liquidated Damages Clause That Will Hold Up?
Smart drafting dramatically increases the odds that your clause survives judicial challenge. Here's what commercial litigators recommend:
Show your math: include a recital in the contract explaining how the parties arrived at the liquidated amount. Courts love seeing that the number resulted from actual negotiation and analysis, not a number pulled from thin air.
Tie the amount to identifiable harm categories: reference specific types of losses the clause is meant to cover (lost revenue, recruitment costs, reputational harm) even if you can't pin down exact numbers.
Acknowledge the difficulty of measurement — a sentence stating that "the parties agree that actual damages from breach would be difficult or impossible to determine with precision" won't guarantee enforceability, but it helps frame the clause favorably.
Keep the amount proportional — the liquidated sum should bear a reasonable relationship to the overall contract value and the foreseeable scope of harm.
Consider a cap or declining scale — a liquidated damages amount that decreases over the contract term (reflecting reduced exposure as performance progresses) is more likely to be seen as a genuine damage estimate.
Make it mutual where possible — clauses that bind both parties are harder to attack as one-sided penalties.
Contracts drafted with AI tools can create disputes of their own. AI can produce a polished generic contract, but if you don't know what you need it to say, it may leave out the terms that protect you, and that gap has become a real source of litigation.
If your business regularly enters into contracts worth $500,000 or more, having a commercial litigation attorney review your liquidated damages provisions before you sign is a sensible step.
Can You Recover Both Liquidated Damages and Actual Damages?
Generally, no. Liquidated damages and actual damages for the same breach are mutually exclusive under New York law. The whole point of a liquidated damages clause is to replace the need to prove actual damages. If you invoke the clause, you get the agreed-upon amount — even if your actual damages were higher.
There are narrow exceptions. If the contract specifies that the liquidated damages cover only certain types of harm (say, delay damages in a construction project), you may still pursue actual damages for other types of harm the clause doesn't address, such as defective workmanship. The key is whether the clause was intended to be the exclusive remedy for all breach-related harm or only for specific categories of loss.
Some contracts also include a clause allowing the non-breaching party to elect between liquidated damages and actual damages at the time of breach. This "election of remedies" approach gives you flexibility but can create litigation over which remedy applies.
When you're facing a significant contract breach, understanding your full range of remedies (including whether to file a lawsuit seeking the liquidated amount or actual damages) requires careful strategic analysis.
Can a court reduce a liquidated damages amount instead of throwing out the clause entirely?
New York courts generally take an all-or-nothing approach: the clause is either enforceable as written or it's struck down as a penalty. Courts don't typically rewrite the clause to impose a "fairer" number. If the provision fails, you fall back on proving actual damages. This makes proper drafting essential — you won't get a second chance to fix the number after litigation begins.
Does it matter who breached first when enforcing a liquidated damages clause?
Yes. If you materially breached the contract before the other side did, you generally can't enforce a liquidated damages clause against them. New York follows the general rule that a party in material breach cannot recover on the contract. However, minor or immaterial breaches on your part typically won't bar enforcement. The question of who breached first, and whether that breach was material, is often the most heavily litigated factual issue in these cases.
Are liquidated damages clauses in consumer contracts treated differently than commercial contracts?
Yes. New York courts apply stricter scrutiny to liquidated damages in consumer contracts, where bargaining power is inherently unequal. In business-to-business agreements between sophisticated commercial parties represented by counsel, courts give more deference to the parties' negotiated terms. The presumption is that two businesses with lawyers had the opportunity to negotiate a fair provision — or walk away from the deal.
How do liquidated damages interact with the duty to mitigate in New York?
One of the major advantages of a valid liquidated damages clause is that it generally eliminates the breaching party's argument that you failed to mitigate. Because the damages are preset by agreement, the non-breaching party doesn't need to prove mitigation efforts. However, if the clause is struck down and you're pursuing actual damages, the duty to mitigate applies in full — and failure to take reasonable steps to reduce your losses can significantly reduce your recovery.
Liquidated damages clauses are powerful tools when drafted correctly and devastating traps when they aren't. Whether a court enforces the agreed amount or sends you into a multi-year damages fight often comes down to a few sentences buried in the contract's boilerplate. To see how Reza Yassi handles disputes over those few sentences, visit the firm's breach of contract page.
If you or your business is dealing with a contract breach involving a liquidated damages provision (whether you're trying to enforce one or defend against one), Reza Yassi at Yassi Law PC is ready to help. Call us today at 646-992-2138 for a consultation.
Written by Reza Yassi | LinkedIn
Prior results do not guarantee a similar outcome.
This article is for informational purposes only and does not constitute legal advice. Although I am an attorney, I am not your attorney, and reading this article does not create an attorney-client relationship. Laws vary by jurisdiction and may have changed since the publication of this article. For advice specific to your situation, consult a qualified attorney.


.png)